NEM Gas Baseload Stats

CCGT and steam-cycle gas thermal plant across the NEM — baseload and mid-merit units, not open-cycle peakers. Stats for the selected period. Data through 03 Aug 2026, 22:55 AEST.

Browse by type
Energy revenue (× MLF)
$413.5k
FCAS revenue (× MLF)
$14
FCAS volume
21.4 MWh
Dispatched
7,588.3 MWh
Capacity factor
11.1%
Generators
11

Energy revenue = cleared MW × (5/60 h) × regional RRP × MLF. FCAS revenue = sum of cleared FCAS MW × (5/60 h) × regional FCAS price × MLF (raise/lower 6s, 60s, 5min, reg). FCAS volume = total FCAS enablement MWh across all services. Capacity factor = dispatched MWh ÷ (nameplate MW × period hours). SRMC from financial assumptions. Not AEMO settlement data.

Site DUID Region Tech Energy rev. (× MLF) FCAS rev. (× MLF) FCAS MWh MWh dispatch MWh available Capacity factor Est. SRMC
Yarwun 1 YARWUN_1 QLD1 Turbine - CCGT $114.6k $0 2,009.5 866.2 46.5% $84.30 View
Pelican Point PPCCGT SA1 Turbine - CCGT $93.0k $0 1,543.9 225.7 12.2% $84.30 View
Osborne OSB-AG SA1 Turbine - CCGT $76.6k $0 764.8 17.7% $84.30 View
Torrens Island B TORRB2 SA1 Turbine - Steam Sub Critical $66.0k $0 902.7 18.8% $5.47 View
Tamar Valley Combined Cycle TVCC201 TAS1 Turbine - CCGT $63.2k $14 21.4 2,367.4 1,092.0 47.4% $84.30 View
Torrens Island B TORRB3 SA1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View
Torrens Island B TORRB4 SA1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View
Tallawarra TALWA1 NSW1 Turbine - CCGT $0 $0 0.0% $84.30 View
Townsville Power Station YABULU2 QLD1 Turbine - CCGT $0 $0 0.0% $84.30 View
Townsville Power Station YABULU QLD1 Turbine - CCGT $0 $0 0.0% $84.30 View
Newport NPS VIC1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View