Open-cycle and peaking gas units across the NEM — OCGT, reciprocating engines, and fast-start gas turbines. Stats for the selected period. Data through 22 Sep 2026, 03:45 AEST.
Energy revenue = cleared MW × (5/60 h) × regional RRP × MLF. FCAS revenue = sum of cleared FCAS MW × (5/60 h) × regional FCAS price × MLF (raise/lower 6s, 60s, 5min, reg). FCAS volume = total FCAS enablement MWh across all services. Capacity factor = dispatched MWh ÷ (nameplate MW × period hours). SRMC from financial assumptions. Not AEMO settlement data.
| Site | DUID | Region | Tech | Energy rev. (× MLF) | FCAS rev. (× MLF) | FCAS MWh | MWh dispatch | MWh available | Capacity factor | Est. SRMC | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Mortlake | MORTLK11 |
VIC1 | Turbine - OCGT | $740.8k | $0 | — | 7,696.2 | 36,629.7 | 15.7% | $128.50 | View |
| Barker Inlet Power Station | BARKIPS1 |
SA1 | Reciprocating Engine - Spark ignition | $461.0k | $0 | — | 5,068.9 | 27,101.6 | 14.4% | $9.00 | View |
| Mortlake | MORTLK12 |
VIC1 | Turbine - OCGT | $203.1k | $0 | — | 1,900.0 | 36,565.7 | 3.9% | $128.50 | View |
| Somerton | AGLSOM |
VIC1 | Turbine - OCGT | $180.3k | $0 | — | 1,699.5 | 15,486.2 | 6.0% | $128.50 | View |
| Quarantine | QPS5 |
SA1 | Turbine - OCGT | $90.7k | $0 | — | 826.6 | 10,355.8 | 3.8% | $209.05 | View |
| Ladbroke Grove | LADBROK2 |
SA1 | Turbine - OCGT | $79.1k | $0 | — | 888.1 | 6,006.4 | 13.2% | $145.06 | View |
| Uranquinty | URANQ13 |
NSW1 | Turbine - OCGT | $72.3k | $0 | — | 535.5 | 20,546.7 | 1.8% | $128.50 | View |
| Uranquinty | URANQ14 |
NSW1 | Turbine - OCGT | $62.9k | $0 | — | 466.4 | 20,501.7 | 1.6% | $128.50 | View |
| Ladbroke Grove | LADBROK1 |
SA1 | Turbine - OCGT | $47.9k | $0 | — | 488.2 | 6,039.5 | 7.3% | $153.02 | View |
| Tamar Valley Peaking | TVPP104 |
TAS1 | Turbine - OCGT | $20.1k | $0 | — | 225.5 | 4,243.7 | 2.3% | $128.50 | View |
| Bell Bay Three | BBTHREE2 |
TAS1 | Turbine - OCGT | $13.2k | $0 | — | 167.7 | 2,333.0 | 2.5% | $137.22 | View |
| Oakey Power Station | OAKEY2 |
QLD1 | Turbine - OCGT | $13.1k | $0 | — | 90.9 | 6,495.7 | 0.3% | $128.50 | View |
| Colongra | CG2 |
NSW1 | Turbine - OCGT | $12.5k | $0 | — | 141.9 | 11,760.6 | 0.5% | $135.55 | View |
| Quarantine | QPS1 |
SA1 | Turbine - OCGT | $10.4k | $0 | — | 115.3 | 2,450.5 | 2.4% | $128.50 | View |
| Quarantine | QPS3 |
SA1 | Turbine - OCGT | $9.4k | $0 | — | 103.5 | 3,076.4 | 2.1% | $128.50 | View |
| Smithfield Energy Facility | SITHE01 |
NSW1 | Turbine - OCGT | $7.0k | $0 | — | 45.3 | — | 0.2% | $128.50 | View |
| Valley Power | VPGS1 |
VIC1 | Turbine - OCGT | $5.3k | $0 | — | 65.2 | 7,868.7 | 0.8% | $128.50 | View |
| Tallawarra B | TALWB1 |
NSW1 | Turbine - OCGT | $4.7k | $0 | — | 145.4 | 45,465.0 | 0.3% | $128.50 | View |
| Bell Bay Three | BBTHREE1 |
TAS1 | Turbine - OCGT | $4.6k | $0 | — | 122.0 | 993.7 | 1.8% | $182.63 | View |
| Hallett GT | AGLHAL |
SA1 | Turbine - OCGT | $1.2k | $0 | — | 39.7 | 25,866.2 | 0.1% | $100.22 | View |
| Mintaro GT | MINTARO |
SA1 | Turbine - OCGT | $57 | $0 | — | 1.5 | 12,481.7 | 0.0% | $128.50 | View |
| Bolivar Power Station | BOLIVPS1 |
SA1 | Turbine - OCGT | $0 | $0 | — | 0.0 | — | 0.0% | $151.37 | View |
| Colongra | CG3 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | 25,419.2 | 0.0% | $144.24 | View |
| Colongra | CG1 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | 25,419.2 | 0.0% | $197.00 | View |
| Colongra | CG4 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | 25,419.2 | 0.0% | $194.33 | View |
| Snapper Point Power Station | SNAPPER1 |
SA1 | Turbine - OCGT | $0 | $0 | — | — | 21,585.0 | 0.0% | $128.50 | View |
| Bell Bay Three | BBTHREE3 |
TAS1 | Turbine - OCGT | $0 | $0 | — | — | 3,319.7 | 0.0% | $141.97 | View |
| Bairnsdale | BDL01 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 6,301.7 | 0.0% | $142.10 | View |
| Bairnsdale | BDL02 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $158.38 | View |
| Barcaldine Power Station | BARCALDN |
QLD1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $141.78 | View |
| Uranquinty | URANQ12 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | 20,583.2 | 0.0% | $128.50 | View |
| Uranquinty | URANQ11 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | 20,326.7 | 0.0% | $128.50 | View |
| Valley Power | VPGS6 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 7,618.4 | 0.0% | $128.50 | View |
| Valley Power | VPGS5 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 7,618.4 | 0.0% | $128.50 | View |
| Valley Power | VPGS4 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $128.50 | View |
| Valley Power | VPGS3 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 8,025.4 | 0.0% | $128.50 | View |
| Valley Power | VPGS2 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 8,025.4 | 0.0% | $128.50 | View |
| Dry Creek GT | DRYCGT1 |
SA1 | Turbine - OCGT | $0 | $0 | — | — | 6,653.2 | 0.0% | $141.50 | View |
| Dry Creek GT | DRYCGT2 |
SA1 | Turbine - OCGT | $0 | $0 | — | — | 5,051.7 | 0.0% | $135.55 | View |
| Dry Creek GT | DRYCGT3 |
SA1 | Turbine - OCGT | $0 | $0 | — | — | 6,927.5 | 0.0% | $210.15 | View |
| Oakey Power Station | OAKEY1 |
QLD1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $128.50 | View |
| Jeeralang B | JLB03 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 11,258.0 | 0.0% | $137.85 | View |
| Laverton North | LNGS2 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 20,652.6 | 0.0% | $128.50 | View |
| Laverton North | LNGS1 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 19,575.7 | 0.0% | $128.50 | View |
| Jeeralang B | JLB02 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 10,825.0 | 0.0% | $137.71 | View |
| Jeeralang B | JLB01 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $128.50 | View |
| Hunter Power Station | HUNTER1 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $142.99 | View |
| Hunter Power Station | HUNTER2 |
NSW1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $152.46 | View |
| Jeeralang A | JLA01 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 7,794.0 | 0.0% | $135.55 | View |
| Jeeralang A | JLA02 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 7,794.0 | 0.0% | $128.50 | View |
| Jeeralang A | JLA03 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 7,794.0 | 0.0% | $141.46 | View |
| Jeeralang A | JLA04 |
VIC1 | Turbine - OCGT | $0 | $0 | — | — | 7,794.0 | 0.0% | $177.20 | View |
| Quarantine | QPS4 |
SA1 | Turbine - OCGT | $0 | $0 | — | — | — | 0.0% | $128.50 | View |
| Roma | ROMA_8 |
QLD1 | Turbine - OCGT | $0 | $0 | — | — | 4,568.2 | 0.0% | $128.50 | View |
| Quarantine | QPS2 |
SA1 | Turbine - OCGT | $0 | $0 | — | — | 3,386.0 | 0.0% | $128.50 | View |
| Roma | ROMA_7 |
QLD1 | Turbine - OCGT | $-601 | $0 | — | 100.8 | 3,925.0 | 1.5% | $128.50 | View |