Energy revenue = cleared MW × (5/60 h) × regional RRP × MLF. FCAS revenue = sum of cleared FCAS MW × (5/60 h) × regional FCAS price × MLF (raise/lower 6s, 60s, 5min, reg). FCAS volume = total FCAS enablement MWh across all services. Capacity factor = dispatched MWh ÷ (nameplate MW × period hours). SRMC from financial assumptions. Not AEMO settlement data.
| Site | DUID | Region | Tech | Energy rev. (× MLF) | FCAS rev. (× MLF) | FCAS MWh | MWh dispatch | MWh available | Capacity factor | Est. SRMC | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Kogan Creek | KPP_1 |
QLD1 | Turbine - Steam Super Critical | $38.91M | $0 | — | 481,196.2 | 521,007.3 | 89.8% | $52.60 | View |
| Eraring | ER04 |
NSW1 | Turbine - Steam Sub Critical | $36.94M | $2.6k | 21,059.1 | 420,002.9 | 491,858.3 | 81.0% | $55.48 | View |
| Bayswater | BW04 |
NSW1 | Turbine - Steam Sub Critical | $33.23M | $3.7k | 11,113.4 | 387,038.4 | 485,494.0 | 78.5% | $55.48 | View |
| Bayswater | BW03 |
NSW1 | Turbine - Steam Sub Critical | $32.96M | $3.2k | 10,394.5 | 382,173.8 | 485,384.2 | 77.5% | $28.68 | View |
| Mt Piper | MP1 |
NSW1 | Turbine - Steam Sub Critical | $32.90M | $0 | — | 364,944.2 | 517,255.8 | 69.4% | $49.24 | View |
| Eraring | ER02 |
NSW1 | Turbine - Steam Sub Critical | $31.61M | $2.0k | 15,904.8 | 363,056.7 | 420,460.8 | 70.0% | $59.45 | View |
| Eraring | ER03 |
NSW1 | Turbine - Steam Sub Critical | $31.02M | $867 | 15,255.3 | 336,558.8 | 390,331.7 | 64.9% | $49.77 | View |
| Bayswater | BW01 |
NSW1 | Turbine - Steam Sub Critical | $30.63M | $3.6k | 10,087.3 | 358,492.0 | 447,075.8 | 75.4% | $53.57 | View |
| Vales Point B | VP5 |
NSW1 | Turbine - Steam Sub Critical | $27.36M | $123 | 317.4 | 305,501.5 | 434,025.5 | 64.3% | $52.60 | View |
| Bayswater | BW02 |
NSW1 | Turbine - Steam Sub Critical | $26.79M | $4.2k | 9,365.0 | 333,796.2 | 453,758.5 | 67.7% | $26.23 | View |
| Loy Yang B | LOYYB1 |
VIC1 | Turbine - Steam Sub Critical | $26.57M | $2.5k | 12,908.0 | 387,863.8 | 414,400.3 | 92.9% | $47.20 | View |
| Loy Yang B | LOYYB2 |
VIC1 | Turbine - Steam Sub Critical | $26.04M | $2.5k | 12,275.0 | 383,485.1 | 406,882.7 | 91.8% | $47.20 | View |
| Loy Yang A Power Station | LYA3 |
VIC1 | Turbine - Steam Sub Critical | $24.99M | $503 | 5,710.6 | 355,951.4 | 393,517.1 | 88.3% | $47.20 | View |
| Loy Yang A Power Station | LYA4 |
VIC1 | Turbine - Steam Sub Critical | $24.48M | $424 | 5,243.5 | 354,586.2 | 388,091.2 | 87.9% | $47.20 | View |
| Vales Point B | VP6 |
NSW1 | Turbine - Steam Sub Critical | $23.15M | $285 | 383.7 | 244,498.2 | 358,798.2 | 51.5% | $52.60 | View |
| Loy Yang A Power Station | LYA2 |
VIC1 | Turbine - Steam Sub Critical | $22.94M | $365 | 1,491.1 | 332,473.6 | 362,101.7 | 87.1% | $47.20 | View |
| Loy Yang A Power Station | LYA1 |
VIC1 | Turbine - Steam Sub Critical | $19.64M | $402 | 4,791.4 | 308,398.7 | 349,354.7 | 76.5% | $47.20 | View |
| Tarong | TARONG#2 |
QLD1 | Turbine - Steam Sub Critical | $18.18M | $1.8k | 1,007.4 | 220,815.6 | 243,292.1 | 87.6% | $55.48 | View |
| Tarong | TARONG#4 |
QLD1 | Turbine - Steam Sub Critical | $17.89M | $1.8k | 1,000.1 | 217,038.4 | 239,182.9 | 86.1% | $52.58 | View |
| Tarong | TARONG#1 |
QLD1 | Turbine - Steam Sub Critical | $16.65M | $44 | 1.7 | 207,994.0 | 226,150.4 | 82.5% | $52.60 | View |
| Millmerran Power Plant | MPP_2 |
QLD1 | Turbine - Steam Super Critical | $16.16M | $0 | — | 211,101.4 | 231,535.0 | 68.8% | $52.60 | View |
| Yallourn W | YWPS3 |
VIC1 | Turbine - Steam Sub Critical | $16.05M | $0 | — | 244,061.3 | 257,155.0 | 90.4% | $47.20 | View |
| Millmerran Power Plant | MPP_1 |
QLD1 | Turbine - Steam Super Critical | $14.98M | $0 | — | 182,785.8 | 201,649.4 | 59.6% | $52.60 | View |
| Yallourn W | YWPS4 |
VIC1 | Turbine - Steam Sub Critical | $14.89M | $0 | — | 217,737.4 | 231,181.2 | 80.6% | $47.20 | View |
| Callide B | CALL_B_2 |
QLD1 | Turbine - Steam Sub Critical | $14.56M | $0 | — | 193,725.5 | 229,780.0 | 76.9% | $55.48 | View |
| Yallourn W | YWPS2 |
VIC1 | Turbine - Steam Sub Critical | $14.27M | $0 | — | 228,222.5 | 227,526.7 | 90.6% | $47.20 | View |
| Callide B | CALL_B_1 |
QLD1 | Turbine - Steam Sub Critical | $13.66M | $432 | 317.8 | 178,679.2 | 229,018.3 | 70.9% | $32.60 | View |
| Darling Downs | DDPS1 |
QLD1 | Turbine - CCGT | $13.40M | $0 | — | 142,810.0 | 159,882.7 | 30.8% | $3.31 | View |
| Stanwell | STAN-2 |
QLD1 | Turbine - Steam Sub Critical | $13.38M | $1.5k | 1,096.4 | 168,875.9 | 230,193.2 | 64.3% | $52.60 | View |
| Stanwell | STAN-1 |
QLD1 | Turbine - Steam Sub Critical | $13.35M | $2.1k | 5,086.0 | 169,771.2 | 215,945.1 | 64.6% | $52.60 | View |
| Mt Piper | MP2 |
NSW1 | Turbine - Steam Sub Critical | $12.80M | $0 | — | 124,358.4 | 204,166.7 | 26.2% | $52.60 | View |
| Stanwell | STAN-4 |
QLD1 | Turbine - Steam Sub Critical | $11.03M | $20 | 64.9 | 141,373.3 | 175,403.8 | 53.8% | $52.60 | View |
| Tarong | TARONG#3 |
QLD1 | Turbine - Steam Sub Critical | $10.92M | $25 | 0.5 | 140,578.2 | 182,529.2 | 55.8% | $55.48 | View |
| Yallourn W | YWPS1 |
VIC1 | Turbine - Steam Sub Critical | $9.69M | $0 | — | 165,467.6 | 171,292.5 | 65.7% | $47.20 | View |
| Swanbank E GT | SWAN_E |
QLD1 | Turbine - CCGT | $8.39M | $743 | 350.4 | 74,412.9 | 97,389.2 | 26.8% | $2.00 | View |
| Gladstone | GSTONE5 |
QLD1 | Turbine - Steam Sub Critical | $8.08M | $250 | 127.3 | 98,051.1 | 165,252.1 | 48.6% | $58.48 | View |
| Gladstone | GSTONE1 |
QLD1 | Turbine - Steam Sub Critical | $6.95M | $68 | 83.4 | 82,998.9 | 148,747.5 | 41.2% | $52.99 | View |
| Stanwell | STAN-3 |
QLD1 | Turbine - Steam Sub Critical | $6.55M | $20 | 38.6 | 70,028.6 | 86,902.7 | 26.6% | $52.60 | View |
| Gladstone | GSTONE4 |
QLD1 | Turbine - Steam Sub Critical | $6.12M | $28 | 59.1 | 80,851.7 | 151,977.4 | 40.1% | $52.60 | View |
| Gladstone | GSTONE6 |
QLD1 | Turbine - Steam Sub Critical | $5.85M | $93 | 77.9 | 63,473.5 | 115,823.2 | 31.5% | $54.96 | View |
| Callide C | CPP_3 |
QLD1 | Turbine - Steam Super Critical | $5.33M | $0 | — | 82,802.8 | 93,550.3 | 27.1% | $44.41 | View |
| Gladstone | GSTONE3 |
QLD1 | Turbine - Steam Sub Critical | $5.10M | $21 | 55.0 | 66,793.0 | 117,283.3 | 33.1% | $128.75 | View |
| Eraring | ER01 |
NSW1 | Turbine - Steam Sub Critical | $4.75M | $272 | 7,703.5 | 83,058.1 | 127,213.7 | 16.0% | $48.29 | View |
| Braemar | BRAEMAR3 |
QLD1 | Turbine - OCGT | $1.58M | $0 | — | 11,828.2 | 127,923.8 | 8.7% | $128.50 | View |
| Condamine A | CPSA |
QLD1 | Turbine - CCGT | $1.28M | $0 | — | 10,165.6 | 11,266.9 | 16.2% | $95.40 | View |
| Braemar 2 Power Station | BRAEMAR5 |
QLD1 | Turbine - OCGT | $691.4k | $0 | — | 6,595.8 | 102,316.8 | 5.3% | $3.14 | View |
| Braemar 2 Power Station | BRAEMAR6 |
QLD1 | Turbine - OCGT | $384.1k | $0 | — | 3,517.6 | 101,612.4 | 2.8% | $133.36 | View |
| Moranbah North | MBAHNTH |
QLD1 | Reciprocating Engine - Spark ignition | $283.5k | $0 | — | 4,291.8 | — | 9.3% | $57.00 | View |
| Braemar 2 Power Station | BRAEMAR7 |
QLD1 | Turbine - OCGT | $163.5k | $0 | — | 1,208.6 | 107,300.8 | 1.0% | $132.25 | View |
| German Creek | GERMCRK |
QLD1 | Reciprocating Engine - Spark ignition | $135.3k | $0 | — | 2,172.5 | — | 6.7% | $122.81 | View |
| Braemar | BRAEMAR2 |
QLD1 | Turbine - OCGT | $126.1k | $0 | — | 888.6 | 94,955.7 | 0.7% | $130.94 | View |
| Braemar | BRAEMAR1 |
QLD1 | Turbine - OCGT | $69.9k | $0 | — | 573.5 | 107,369.2 | 0.4% | $133.75 | View |
| Callide C | CPP_4 |
QLD1 | Turbine - Steam Super Critical | $0 | $0 | — | — | — | 0.0% | $101.94 | View |
| Gladstone | GSTONE2 |
QLD1 | Turbine - Steam Sub Critical | $0 | $0 | — | — | — | 0.0% | $49.17 | View |
| Tarong North | TNPS1 |
QLD1 | Turbine - Steam Super Critical | $-117 | $0 | — | -2.3 | — | 0.0% | $52.60 | View |