| Capex total (greenfield) |
$210.97M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW |
$4,906,290
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$1.81M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$42,194
Shown in table Reported / source value |
| Variable OPEX / MWh |
$2.11
Shown in table Reported / source value |
| Fuel cost / GJ default |
$12.00
Shown in table |
| Heat rate GJ/MWh default |
10.50
Shown in table |
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 08 Jun 2026
Notes
Plant-specific reported investment found in ExxonMobil Australia/LinkedIn opening remarks: $200 million investment for the Hastings Generation Site. Capacity confirmed at 43 MW. Construction commenced June 2023; commercial operations due to commence as soon as 1 April 2024. The site is expected to operate for 11 years (2024-2034). No reliable plant-specific O&M, fuel, heat-rate, or emissions-intensity source was found in the retrieved results, so server-side defaults and blanks were retained where appropriate.