Solar · Lightsource Development Services Australia Pty Ltd · Solar PV - Fixed
13 Jun 2026 22:50 → 14 Jun 2026 22:50 AEST
| Capex total (greenfield) |
$685.65M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW |
$1,714,135
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$6.08M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$18,987
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$0.21
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
$0.00
Shown in table Reported / source value |
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 08 Jun 2026
Notes
Plant-specific development cost found in NSW planning documents for Gundary Solar Farm: AUD650 million estimated development cost (excl GST). Public sources describe the project as 400MWdc / 320MWac, with no commissioned online date yet available; the project was still in planning / development as of 2026 sources. Fixed OPEX is a server-side default applied due to lack of plant-specific O&M evidence.