16 May 2026 02:20 → 15 Jun 2026 02:20 AEST
| Capex total (greenfield) |
$928.27M
Shown in table Reported / source value How this was derived |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$2,320,675
Shown in table Reported / source value How this was derived |
| Fixed OPEX (annual) |
$23.21M
Shown in table Reported / source value How this was derived |
| Fixed OPEX / MW-yr |
$58,017
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$0.53
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: estimated · AI checked 06 Jun 2026
Notes
No plant-specific greenfield capex announcement was found in the searched sources, so AEMO/CSIRO-style fallback assumptions were used for capex and O&M. Onshore wind has no fuel cost and zero direct emissions. Owner listed in NEMStats as Tetris Energy; project status publicly announced; capacity 400 MW.