Solar · Genaspi Energy Group Pty Ltd · Solar PV - Fixed
13 Jun 2026 19:45 → 14 Jun 2026 19:45 AEST
| Capex total (greenfield) |
$551.16M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$1,160,338
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$6.26M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$13,186
Shown in table Reported / source value |
| Variable OPEX / MWh default |
$0.20
Shown in table |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: low · Status: ai estimated · Capex basis: default · AI checked 05 Jun 2026
Notes
No plant-specific greenfield capex announcement was found in the searched owner/developer/government sources. The project website confirms Genaspi Energy Group is developing the Bundey BESS and Solar Project and describes it as a four-stage project, but does not publish a total project cost. AEMO 2024 cost review provides a solar PV fixed-tilt O&M benchmark of A$12,500/MWp-year, used here only as an operating default; capex was left blank rather than using a benchmark because the user requested project-specific capex first. The current public project page indicates a much larger proposed multi-stage project than the 475 MW solar capacity provided, so this record may represent only part of the broader precinct.