Yendon Wind Farm (YENDWF1)

Wind · Northleaf /InfraRed/Macquarie Capital · Wind Turbine - Onshore

Operational AEMO: In Service VIC1 Wind - Wind NEM data · 24 hours
144 MW
Registered nameplate capacity
24 hours revenue
$6.8k
Capacity factor
19.3%
Revenue / MWh
$10.09
Est. SRMC
$0.50/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. VIC1 regional price (RRP) on right axis.

Key information
Capacity
144 MW

AEMO status In Service
Project status Operational (AI)

Atmos Renewables asset page (2022) describes Yendon as an operating wind farm asset; commissioned 2021-01-01.

Region VIC1
Coordinates -37.63530, 144.01920 (AI)

The Wind Power lists coordinates for Lal Lal/Yendon wind farm near Yendon, Victoria: 37°38'7.1"S 144°1'9.3"E.

MLF 0.9537
DUID YENDWF1
Owner Northleaf /InfraRed/Macquarie Capital
Commissioned Jan 2021
Expected closure 2049
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM Vestas
Turbine model V136/3450
Equipment confidence high
Stats window
19 Jun 2026 00:00 → 19 Jun 2026 23:59 AEST

Dispatch & revenue

19 Jun 2026 00:00 → 19 Jun 2026 23:59 AEST

Energy revenue (× MLF)
$6.8k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
669.0 MWh
Available
549.7 MWh
Curtailed
197.2 MWh
Curtailment
35.9%
of available
MLF used
0.9537
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9425
2025-07-01 0.9537

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
144 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.50/MWh
Capex total (greenfield) default
$317.68M

Shown in table
$317.68M (2026 real AUD)

Capex refurbishment
Capex / MW default
$2,200,000

Shown in table
$2.20M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$0.50

Shown in table
$0.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: unknown · Status: needs review · Capex basis: unknown