07 Jun 2026 01:55 → 14 Jun 2026 01:55 AEST
| Capex total (greenfield) |
$504.10M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage |
—
|
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr |
$26,951
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$8.54
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Project-specific reported investment was found in Iberdrola's acquisition announcement for the Tungkillo battery storage project: €275 million, converted here to approximately A$492 million using the contemporaneous EUR/AUD magnitude implied by the announcement context. The source does not state a separate EPC/construction cost, so this is the best available project-specific investment figure but it is an acquisition/investment amount rather than a fully itemised owner construction budget. Site capacity is up to 270 MW / 1,080 MWh; no plant-specific fixed O&M or asset life was found, so AEMO/Aurecon battery benchmark O&M is used as fallback. No fuel cost applies to battery storage.