Sundown SF(Canadian Solar)

Solar · Canadian Solar · Solar PV - Fixed

AEMO: removed Solar - Solar NEM data · 24 hours
360 MW
Registered nameplate capacity
Est. SRMC
$0.00/MWh
Key information
Capacity
360 MW

AEMO status removed
Project status (AI)

Coordinates

DUID
Owner Canadian Solar
Commissioned
Expected closure
Closure date
Technology Solar PV - Fixed
Fuel Solar - Solar
Module OEM
Module / inverter supplier
Inverter OEM
Inverter model
Stats window
14 Jun 2026 00:15 → 15 Jun 2026 00:15 AEST

Dispatch & revenue

14 Jun 2026 00:15 → 15 Jun 2026 00:15 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (fixed)
Capacity
360 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$752.18M

Shown in table
$752.18M (2026 real AUD)

Reported / source value
$689.00M (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
A submission filed on the NSW Planning Portal states the project's capital investment value is approximately $689 million.

Reference
Director-Energy Assessments submission on Sundown Solar Farm (medium confidence)
Source recorded 05 Jun 2026

Capex refurbishment
Capex / MW derived
$2,089,398

Shown in table
$2.09M (2026 real AUD)

Reported / source value
$1.91M (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated from the reported capital investment value and the 360 MW capacity.

Reference
Director-Energy Assessments submission on Sundown Solar Farm (medium confidence)
Source recorded 05 Jun 2026

Fixed OPEX (annual)
$5.90M

Shown in table
$5.90M (2026 real AUD)

Reported / source value
$5.40M (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated as 15,000 × 360 MW.

Reference
2024 Energy Technology Cost and Technical Parameter Review - Solar (medium confidence)
Source recorded 05 Jun 2026

Fixed OPEX / MW-yr
$16,376

Shown in table
$16.4k (2026 real AUD)

Reported / source value
$15.0k (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO/Aurecon benchmark for 1MW rooftop solar PV, used as a fallback for lack of plant-specific O&M.

Reference
2024 Energy Technology Cost and Technical Parameter Review - Solar (high confidence)
Source recorded 05 Jun 2026

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Solar PV variable O&M is treated as nil because the benchmark says it is included in fixed O&M.

Reference
2024 Energy Technology Cost and Technical Parameter Review - Solar (low confidence)
Source recorded 05 Jun 2026

Fuel cost / GJ
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 05 Jun 2026

Notes
Project is a 360 MW solar farm with a 150 MW/4h BESS in NSW. Plant-specific capital investment value of approximately $689 million appears in a submission referencing the project; no clearer owner-issued construction cost announcement was found in the available sources. Fixed O&M defaulted to AEMO/Aurecon 2024 benchmark for a 4.99 MW ground-mount solar PV project because no plant-specific O&M was found. Variable O&M for solar is treated as negligible.