BESS · Shell New Energies Australia Pty Ltd · Storage - Battery
14 Jun 2026 06:05 → 15 Jun 2026 06:05 AEST
| Capex total (greenfield) |
$44.30M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage derived |
$369,198
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$1.37M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$22,785
Shown in table Reported / source value |
| Variable OPEX / MWh |
$0.00
Shown in table Reported / source value |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 06 Jun 2026
Notes
Riverina Energy Storage System 1 is a 60MW/120MWh battery partition within the broader Riverina project. Public sources identified the asset and its operation, but I did not find a project-specific total construction/investment cost for this 60MW tranche. As a fallback, battery O&M values were derived from AEMO's 2024 Energy Technology Cost and Technical Parameter Review; capex was left blank because no reliable plant-specific or benchmark figure was requested to be substituted without explicit need.