Rangebank BESS (RANGEB1)

BESS · Cranbourne BESS Project Co Pty Ltd · Storage - Battery

Commissioning AEMO: In Service VIC1 Other - Other NEM data · 30 days
200/400 MW
Registered nameplate capacity / storage
30 days revenue
$637.8k
Capacity factor
-1.2%
Revenue / MWh
—
Est. SRMC
$1.50/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. VIC1 regional price (RRP) on right axis.

Key information
Capacity
200 MW / 400 MWh

AEMO status In Service
Project status Commissioning (AI)

pv magazine Australia, 2024-08-08: Rangebank BESS energised and scheduled to be fully operational by late 2024.

Region VIC1
Coordinates -38.11600, 145.22600 (AI)

Shell Energy project page: 5 Battery Court (enter via 1120 Thompsons Rd), Cranbourne West, Victoria, Australia.

MLF 0.9957
DUID RANGEB1
Owner Cranbourne BESS Project Co Pty Ltd
Commissioned Oct 2024
Expected closure 2044
Closure date —
Technology Storage - Battery
Fuel Other - Other
Battery OEM Fluence
Battery platform / chemistry Gridstack
Inverter OEM —
Inverter / PCS model —
Equipment confidence high
Stats window
26 Aug 2026 18:15 → 25 Sep 2026 18:15 AEST

Dispatch & revenue

26 Aug 2026 18:15 → 25 Sep 2026 18:15 AEST

Energy revenue (× MLF)
$637.8k
FCAS revenue (× MLF)
$68
FCAS volume
14.0 MWh
Dispatched
-1,676.9 MWh
Available
77,896.7 MWh
Curtailed
79,664.3 MWh
Curtailment
102.3%
of available
MLF used
0.9957
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

🔋 State of charge

Stored energy at the start of each 5‑minute interval (AEMO INITIAL_ENERGY_STORAGE). Available up to the latest next‑day dispatch file.

65.4 MWh 16%
at 25 Sep 03:15 · of 400 MWh registered

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional price — dispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • State of charge — INITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-08-13 0.9955
2025-07-01 0.9961
2026-07-01 0.9957

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
200 MW / 400 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield) default
$140.00M

Shown in table
$140.00M (2026 real AUD)

Capex refurbishment
—
Capex / MWh storage default
$350,000

Shown in table
$350.0k (2026 real AUD)

Fixed OPEX (annual)
—
Fixed OPEX / MW-yr default
$25,000

Shown in table
$25.0k (2026 real AUD)

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
—
Heat rate GJ/MWh
—

Confidence: unknown · Status: needs review · Capex basis: unknown