New England Solar Farm (NEWENSF1)

Solar · ACEN AUSTRALIA · Solar PV - Single axis tracking

Operational AEMO: In Service NSW1 Solar - Solar NEM data · 24 hours
200 MW
Registered nameplate capacity
Est. SRMC
$0.25/MWh
Key information
Capacity
200 MW

AEMO status In Service
Project status Operational (AI)

ACEN Australia project page states Stage 1 completed in 2023 and the project status as Operating; NSW Govt notes the asset is in service/operating.

Region NSW1
Coordinates -30.03900, 151.64900 (AI)

Project documents and ICN/ACEN materials place the site approximately 6 km east of Uralla, NSW; exact on-site coordinates not clearly documented in the provided sources.

DUID NEWENSF1
Owner ACEN AUSTRALIA
Commissioned May 2023
Expected closure 2073
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM
Module / inverter supplier module / inverter supplier not documented
Inverter OEM
Inverter model
Equipment confidence low
Stats window
22 Jun 2026 00:00 → 22 Jun 2026 00:00 AEST

Dispatch & revenue

22 Jun 2026 00:00 → 22 Jun 2026 00:00 AEST

No dispatch data for DUID NEWENSF1 in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
200 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.25/MWh
Capex total (greenfield) default
$260.00M

Shown in table
$260.00M (2026 real AUD)

Capex refurbishment
Capex / MW default
$1,300,000

Shown in table
$1.30M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$20,000

Shown in table
$20.0k (2026 real AUD)

Variable OPEX / MWh default
$0.25

Shown in table
$0.25 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: unknown · Status: needs review · Capex basis: unknown