Mokoan Solar Farm (MOKOSF1)

Solar · EE Solar 6 Pty Ltd as trustee for EE Solar 6 Trust · Solar PV - Single axis tracking

AEMO: removed VIC1 Solar - Solar NEM data · 17h
46 MW
Registered nameplate capacity
17h revenue
$1.1k
Capacity factor
3.1%
Revenue / MWh
$44.42
Est. SRMC
$0.25/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. VIC1 regional price (RRP) on right axis.

Key information
Capacity
46 MW

AEMO status removed
Project status (AI)

Region VIC1
Coordinates

MLF 0.9415
DUID MOKOSF1
Owner EE Solar 6 Pty Ltd as trustee for EE Solar 6 Trust
Commissioned Apr 2025
Expected closure 2025
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM
Module / inverter supplier
Inverter OEM
Inverter model
Stats window
15 Jun 2026 00:00 → 15 Jun 2026 17:25 AEST

Dispatch & revenue

15 Jun 2026 00:00 → 15 Jun 2026 17:25 AEST

Energy revenue (× MLF)
$1.1k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
24.2 MWh
Available
MWh
Curtailed
MWh
Curtailment
of available
MLF used
0.9415
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-11-26 0.9484
2025-07-01 0.9415

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
46 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.25/MWh
Capex total (greenfield) default
$59.80M

Shown in table
$59.80M (2026 real AUD)

Capex refurbishment
Capex / MW default
$1,300,000

Shown in table
$1.30M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$20,000

Shown in table
$20.0k (2026 real AUD)

Variable OPEX / MWh default
$0.25

Shown in table
$0.25 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: unknown · Status: needs review · Capex basis: unknown