01 Jun 2026 00:00 → 14 Jun 2026 06:20 AEST
| Capex total (greenfield) |
$379.10M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage |
—
|
| Fixed OPEX (annual) |
$2.56M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$25,615
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$1.54
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 08 Jun 2026
Notes
No plant-specific battery-only capex was found from the owner/developer/trust; the best available reported figure is the SEC's $370 million investment for the integrated Horsham energy park. Battery capacity is 100 MW / 200 MWh. Commissioning is targeted for 2027. Fixed OPEX uses server-side fallback because no project-specific O&M source was found. Emissions intensity set to zero for battery storage.