14 Jun 2026 00:00 → 14 Jun 2026 01:55 AEST
| Capex total (greenfield) |
—
|
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage |
$369,198
Shown in table Reported / source value |
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr default |
$25,000
Shown in table |
| Variable OPEX / MWh default |
$1.50
Shown in table |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: low · Status: ai estimated · Capex basis: default · AI checked 08 Jun 2026
Notes
No project-specific greenfield capex announcement was found for Great Lakes Battery in owner or government sources. The project website states the battery will be up to 280 MW / 560 MWh and privately financed by Neoen, with construction expected to take around 18 months once commenced. The website also states battery technology typically has an industry-leading 20-year warranty. In the absence of a plant-specific capex figure, no benchmark capex has been inserted here because the request prioritised project-specific sources and asked not to use AEMO benchmarks unless necessary.