13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST
| Capex total (greenfield) |
—
|
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage |
$369,198
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$2.03M
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX / MW-yr |
$13,502
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$0.00
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 08 Jun 2026
Notes
No plant-specific greenfield capex announcement was found in the searched owner/developer/government sources. Fallback operating assumptions are based on AEMO 2024 battery benchmark values for a 200 MW BESS; fixed O&M was scaled to the stated 150 MW site capacity. Golden Plains BESS is publicly described as a 150 MW / 600 MWh project planned to commence construction in late 2025.