Golden Fleece BESS

BESS · EIWA Gin Gin Renewable Energy Park Pty Ltd · Storage - Battery

AEMO: removed Solar - Solar NEM data · 30 days
300 MW
Registered nameplate capacity
Est. SRMC
$0.00/MWh
Key information
Capacity
300 MW

AEMO status removed
Project status (AI)

Coordinates

DUID
Owner EIWA Gin Gin Renewable Energy Park Pty Ltd
Commissioned
Expected closure
Closure date
Technology Storage - Battery
Fuel Solar - Solar
Module OEM
Module / inverter supplier
Inverter OEM
Inverter model
Stats window
16 May 2026 03:35 → 15 Jun 2026 03:35 AEST

Dispatch & revenue

16 May 2026 03:35 → 15 Jun 2026 03:35 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (fixed)
Capacity
300 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$348.10M

Shown in table
$348.10M (2026 real AUD)

Reported / source value
$330.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
Capex / MW derived
$1,160,338

Shown in table
$1.16M (2026 real AUD)

Reported / source value
$1.10M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$1.71M

Shown in table
$1.71M (2026 real AUD)

Reported / source value
$1.62M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$5,696

Shown in table
$5.7k (2026 real AUD)

Reported / source value
$5.4k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: low · Status: ai estimated · Capex basis: default · AI checked 08 Jun 2026

Notes
Project-specific greenfield capex not found. Site appears listed as publicly announced 300 MW battery at EIWA Gin Gin Renewable Energy Park Pty Ltd, but no reliable primary-source cost disclosure was located. The only quantified OPEX assumption used is the AEMO/Aurecon 2024 BESS benchmark fixed O&M for the 1-hour case; variable O&M is shown as nil in the benchmark. Because storage duration was unavailable, capex per MWh and any total project cost estimate were not derived.

Sources