01 Jun 2026 00:00 → 18 Jun 2026 02:55 AEST
| Capex total (greenfield) |
$1,033.76M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage derived |
$369,198
Shown in table Reported / source value |
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr default |
$25,000
Shown in table |
| Variable OPEX / MWh |
$1.58
Shown in table Reported / source value |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 07 Jun 2026
Notes
ACEN’s Deeargee/Deargee project is publicly described as a proposed 320 MW solar and battery project, with battery storage up to 1,400 MW AC two-hour or 700 MW AC four-hour configuration. I could not find a plant-specific greenfield capital cost announcement from ACEN, government, or project finance sources in the available search results, so no capex value is reported. For battery assumptions, I used AEMO/Aurecon 2024 BESS benchmark technical parameters: 4-hour BESS EPC cost $324.1M for a 200 MW system, indicative round-trip efficiency ~85%, and 20-year design life; however, these are not treated as project-reported capex. Variable O&M uses the provided default fallback because the AEMO BESS benchmark excerpt available did not expose a comparable variable O&M figure.