| Capex total (greenfield) |
$67.88M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$3,428,136
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$1.52M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$76,816
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$0.70
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026
Notes
Greenfield construction cost sourced from Windlab prospectus case study: total construction cost $48.6 million for 19.8 MW, with construction commencing in 2015 and operation beginning 1 April 2016. No plant-specific refurbishment cost found. Fixed OPEX and variable OPEX fall back to provided internal defaults; wind has no fuel or heat rate.