Collinsville Coal Fired Power Station Project - KCI

Coal · Shine Energy · Other - Other

Development AEMO: Publicly Announced Fossil - Black Coal NEM data · 24 hours
990 MW
Researched capacity
Est. SRMC
$52.60/MWh
Key information
Capacity (AI)
990 MW

AEMO spreadsheet entry for Collinsville Coal Fired Power Station Project - KCI (publicly announced/anticipated capacity listed as 990 MW); no separate primary-source capacity announcement was found in the provided search results.

AEMO status Publicly Announced
Project status Development (AI)

AEMO spreadsheet labels the asset as "Publicly Announced"; no primary-source evidence found that it has progressed to construction or commissioning.

Coordinates

DUID
Owner Shine Energy
Commissioned
Expected closure
Closure date
Technology Other - Other
Fuel Fossil - Black Coal
Equipment OEM
Equipment type / model Other / coal-fired power station project (model not identified)
Equipment confidence low
Stats window
14 Jun 2026 11:45 → 15 Jun 2026 11:45 AEST

Dispatch & revenue

14 Jun 2026 11:45 → 15 Jun 2026 11:45 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Black coal
Capacity
990 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$52.60/MWh
Capex total (greenfield)
$2,604.17M

Shown in table
$2,604.17M (2026 real AUD)

Reported / source value
$2,000.00M (2019 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Independent media corroborates the $2 billion estimate.

Reference
New Qld coal plant years in the works: CEO (medium confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MW derived
$2,630,471

Shown in table
$2.63M (2026 real AUD)

Reported / source value
$2.02M (2019 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$4.00

Shown in table
$4.00 (2026 real AUD)

Fuel cost / GJ default
$4.50

Shown in table
$4.50 (2026 real AUD)

Heat rate GJ/MWh default
10.80

Shown in table
$10.80 (2026 real AUD)

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Plant-specific greenfield capex was found in Shine Energy materials and media coverage citing the developer: proposed cost about $2 billion for a ~1000 MW Collinsville coal-fired power station. No authoritative project-specific operating cost, heat rate, emissions intensity, or fuel contract data was located in the searched sources. AEMO technical reports confirm the Collinsville project is the only coal-fired development in progress in Australia, but those reports were not used for reported capex because a project-specific announcement exists. The project appears to remain proposed/under feasibility rather than commissioned.

Sources