Clements Gap - BESS

BESS · Pacific Hydro Clements Gap Pty Ltd · Storage - Battery

Development AEMO: Committed Other - Other NEM data · 24 hours
60/120 MW
Registered nameplate capacity / storage
Est. SRMC
$1.58/MWh
Key information
Capacity
60 MW / 120 MWh

AEMO status Committed
Project status Development (AI)

Coordinates

DUID
Owner Pacific Hydro Clements Gap Pty Ltd
Commissioned May 2026
Expected closure 2046
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM
Battery platform / chemistry
Inverter OEM
Inverter / PCS model
Stats window
13 Jun 2026 01:25 → 14 Jun 2026 01:25 AEST

Dispatch & revenue

13 Jun 2026 01:25 → 14 Jun 2026 01:25 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
60 MW / 120 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.58/MWh
Capex total (greenfield)
$105.49M

Shown in table
$105.49M (2026 real AUD)

Reported / source value
$100.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Reports the project investment as $100 million for the Clements Gap BESS.

Reference
Pacific Blue starts build of 60 MW battery in South Australia (high confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MWh storage derived
$879,044

Shown in table
$879.0k (2026 real AUD)

Reported / source value
$833.3k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Derived capex per MWh using the site page's 120 MWh capacity figure.

Reference
Clements Gap battery (medium confidence)
Source recorded 06 Jun 2026

Fixed OPEX (annual)
$1.58M

Shown in table
$1.58M (2026 real AUD)

Reported / source value
$1.50M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$26,371

Shown in table
$26.4k (2026 real AUD)

Reported / source value
$25.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Server-side fallback default provided by user; not sourced from web.

Variable OPEX / MWh
$1.58

Shown in table
$1.58 (2026 real AUD)

Reported / source value
$1.50 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Server-side fallback default provided by user; not sourced from web.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Pacific Blue stated the project is a $100 million, 60 MW / 130 MWh grid-scale battery at Clements Gap; this is a reported project investment figure. Later Pacific Blue material describes the battery as 60 MW / 120 MWh, so the reported cost is paired here with the announced 60 MW project capacity and the 2024 construction start year. Operational lifespan noted by Pacific Blue is 20 years.

Sources