Challicum Hills

Wind · Pacific Hydro Challicum Hills Pty Ltd · Wind Turbine - Onshore

Operational AEMO: In Service Wind - Wind NEM data · 7 days
53 MW
Registered nameplate capacity
Est. SRMC
$0.95/MWh
Key information
Capacity
53 MW

AEMO status In Service
Project status Operational (AI)

Coordinates

DUID
Owner Pacific Hydro Challicum Hills Pty Ltd
Commissioned
Expected closure 2030
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM
Turbine model
Stats window
15 Jun 2026 05:50 → 22 Jun 2026 05:50 AEST

Dispatch & revenue

15 Jun 2026 05:50 → 22 Jun 2026 05:50 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
53 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.95/MWh
Capex total (greenfield)
$143.94M

Shown in table
$143.94M (2026 real AUD)

Reported / source value
$76.00M (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Owner/operator page reports the project cost as A$76 million.

Reference
Challicum Hills wind farm | Pacific Blue (high confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MW derived
$2,741,703

Shown in table
$2.74M (2026 real AUD)

Reported / source value
$1.45M (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$5.47M

Shown in table
$5.47M (2026 real AUD)

Reported / source value
$2.89M (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$104,167

Shown in table
$104.2k (2026 real AUD)

Reported / source value
$55.0k (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No site-specific fixed O&M found; server-side default used.

Variable OPEX / MWh
$0.95

Shown in table
$0.95 (2026 real AUD)

Reported / source value
$0.50 (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No site-specific variable O&M found; server-side default used.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Pacific Blue states the Challicum Hills wind farm was a A$76 million project and that construction commenced in October 2002; the site was completed in August 2003. No plant-specific refurbishment cost found. Fixed OPEX used server fallback because no site-specific O&M figure was found in the searches.

Sources