Canunda (CNUNDAWF)

Wind · Canunda Power Pty Ltd · Wind Turbine - Onshore

Operational AEMO: In Service SA1 Wind - Wind NEM data · 0h
46 MW
Registered nameplate capacity
Est. SRMC
$0.50/MWh
Key information
Capacity
46 MW

AEMO status In Service
Project status Operational (AI)

ENGIE Canunda Wind Farm page (accessed 2026): describes Canunda as an operating wind farm producing electricity in South Australia.

Region SA1
Coordinates -37.88400, 140.33800 (AI)

ENGIE Canunda Wind Farm page: located just south of Millicent in South Australia; corroborated by project listings and map references.

DUID CNUNDAWF
Owner Canunda Power Pty Ltd
Commissioned
Expected closure 2035
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM Vestas
Turbine model V52-850
Equipment confidence high
Stats window
15 Jun 2026 00:00 → 15 Jun 2026 00:15 AEST

Dispatch & revenue

15 Jun 2026 00:00 → 15 Jun 2026 00:15 AEST

No dispatch data for DUID CNUNDAWF in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
46 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.50/MWh
Capex total (greenfield)
$167.57M

Shown in table
$167.57M (2026 real AUD)

Reported / source value
$92.50M (2004 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Plant-specific greenfield construction cost reported by a project communications firm describing the owner/developer launch event.

Reference
Canunda Wind Farm (high confidence)
Source recorded 05 Jun 2026

Capex refurbishment
Capex / MW derived
$3,642,880

Shown in table
$3.64M (2026 real AUD)

Reported / source value
$2.01M (2004 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Derived capex per MW using the reported project cost and the registered 46 MW capacity.

Reference
Canunda Wind Farm (high confidence)
Source recorded 05 Jun 2026

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$0.50

Shown in table
$0.50 (2026 real AUD)

Fuel cost / GJ
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2004 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 05 Jun 2026

Notes
Canunda Wind Farm was reported as a $92.5 million project commencing construction in April 2004 and launching in March 2005. The site has 46 MW installed capacity. No separate plant-specific refurbishment capex or O&M figures were found in the searched sources.

Sources