Callide Solar Power Station BESS

BESS · Edify Energy Pty Ltd · Storage - Battery

Development AEMO: Publicly Announced Other - Other NEM data · 24 hours
210/200 MW
Researched capacity / storage
Est. SRMC
$1.50/MWh
Key information
Capacity (AI)
210 MW / 200 MWh

AEMO registration spreadsheet / project references for Callide Solar Power Station BESS list 210 MW and 200 MWh.

AEMO status Publicly Announced
Project status Development (AI)

Edify Energy / project announcements indicate the Callide Solar Power Station BESS is publicly announced and not yet in operation (project planning stage).

Coordinates

DUID
Owner Edify Energy Pty Ltd
Commissioned
Expected closure
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM Tesla
Battery platform / chemistry Megapack
Inverter OEM Tesla
Inverter / PCS model Megapack inverter/PCS
Equipment confidence low
Stats window
12 Jun 2026 22:35 → 13 Jun 2026 22:35 AEST

Dispatch & revenue

12 Jun 2026 22:35 → 13 Jun 2026 22:35 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
210 MW / 200 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield)
$71.72M

Shown in table
$71.72M (2026 real AUD)

Reported / source value
$70.00M (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
The owner project page did not provide a total project cost, so capex_total_aud remains null.

Reference
Callide - Edify Energy (high confidence)
Source recorded 05 Jun 2026

Capex refurbishment
Capex / MWh storage derived
$358,607

Shown in table
$358.6k (2026 real AUD)

Reported / source value
$350.0k (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$10.90M

Shown in table
$10.90M (2026 real AUD)

Reported / source value
$10.64M (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$51,913

Shown in table
$51.9k (2026 real AUD)

Reported / source value
$50.7k (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 05 Jun 2026

Notes
No project-specific greenfield capex figure was found in searched owner/government sources for Callide Solar Power Station BESS. The site page confirms the project remains in development phase and indicates construction is anticipated in FY2025/26, with up to 200MW / 800MWh storage. In the absence of a reported plant-specific investment value, operating assumptions were set using AEMO/Aurecon 2024 battery storage benchmarks for a co-located 200MW BESS case. The benchmark provides indicative EPC cost and fixed O&M; I used the 200MW co-located case and scaled fixed O&M to the site's 210MW battery capacity. Variable O&M is not typically specified for BESS in the benchmark, so it remains null. 90% round-trip efficiency and 25-year life are from the AEMO/Aurecon battery assumptions.

Sources