Bungama BESS (ARENA )

BESS · Bungama Bess Trust · Storage - Battery

Development AEMO: Publicly Announced Other - Other NEM data · 2h
200/400 MW
Researched capacity / storage
Est. SRMC
$1.50/MWh
Key information
Capacity (AI)
200 MW / 400 MWh

AEMO spreadsheet value supplied in prompt (no independent project-source result returned).

AEMO status Publicly Announced
Project status Development (AI)

No project-specific delivery evidence provided; Publicly Announced status indicates a pre-construction stage rather than operation.

Coordinates

DUID
Owner Bungama Bess Trust
Commissioned
Expected closure
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM
Battery platform / chemistry Battery platform / chemistry not documented
Inverter OEM
Inverter / PCS model
Equipment confidence low
Stats window
14 Jun 2026 00:00 → 14 Jun 2026 01:55 AEST

Dispatch & revenue

14 Jun 2026 00:00 → 14 Jun 2026 01:55 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
200 MW / 400 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield)
$147.68M

Shown in table
$147.68M (2026 real AUD)

Reported / source value
$140.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
Capex / MWh storage derived
$369,198

Shown in table
$369.2k (2026 real AUD)

Reported / source value
$350.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$2.70M

Shown in table
$2.70M (2026 real AUD)

Reported / source value
$2.56M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$13,502

Shown in table
$13.5k (2026 real AUD)

Reported / source value
$12.8k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 05 Jun 2026

Notes
No plant-specific greenfield capex figure was found in the searched owner/developer, ARENA, or project-financing sources. The project is reported as a 200 MW / 400 MWh battery within ARENA’s large-scale battery round, while Revera Energy’s current project page describes the broader Bungama BESS project as 250 MW / 500 MWh with operations expected by 2026. O&M uses AEMO/Aurecon 2024 BESS assumptions for a 200 MW, 4-hour BESS with dedicated grid connection; fixed O&M is taken from the 4-hour case and multiplied by 200 MW. Emissions are zero for battery storage on direct operational basis.

Sources