Broadsound_BESS

BESS · Broadsound Solar Farm Pty Ltd · Storage - Battery

Anticipated Other - Other NEM data · 24 hours
240/360 MW
Registered nameplate capacity / storage
Est. SRMC
$1.75/MWh
Key information
Capacity
240 MW / 360 MWh
Status Anticipated
Lifecycle Pre-operating
DUID
Owner Broadsound Solar Farm Pty Ltd
Commissioned Jan 2027
Expected closure
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM
Battery platform / chemistry
Inverter OEM
Inverter / PCS model
Stats window
03 Jun 2026 16:30 → 04 Jun 2026 16:30 AEST

Dispatch & revenue

03 Jun 2026 16:30 → 04 Jun 2026 16:30 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
240 MW / 360 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.75/MWh
Capex total (greenfield)
$527.43M

Source value
$500.00M (2024 nominal)

How this was derived
Provides context that Iberdrola referenced Broadsound within its Australian investment program, though it does not specifically state BESS-only cost.

Reference
Iberdrola starts up the world's first wind-solar hybrid plant in Australia (medium confidence)

Capex refurbishment
Capex / MW
$2,197,609

Source value
$2.08M (2024 nominal)

Capex / MWh storage
$1,465,073

Source value
$1.39M (2024 nominal)

Fixed OPEX (annual)
$7.01M

Source value
$6.00M (2022 nominal)

Fixed OPEX / MW-yr
$29,206

Source value
$25.0k (2022 nominal)

How this was derived
No project-specific battery fixed O&M was found in the searched sources.

Variable OPEX / MWh
$1.75

Source value
$1.50 (2022 nominal)

How this was derived
No project-specific battery variable O&M was found in the searched sources.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 04 Jun 2026

Notes
No plant-specific battery-only capex announcement was found. The reported A$500m investment appears to cover the full Broadsound Solar Farm and Battery project (solar + BESS), not the battery alone. I therefore allocate the full reported project cost to this generator as a proxy, but this likely overstates BESS-only capex. Registered battery output is 240MW with 360MWh storage; project documents also describe the BESS as 180MW/360MWh. Use with caution.