Bowmans Creek Wind Farm

Wind · ARK Energy Corporation Pty Ltd · Wind Turbine - Onshore

Development AEMO: Publicly Announced Wind - Wind NEM data · 24 hours
Registered nameplate capacity — refresh AI for MW/MWh
Est. SRMC
$0.53/MWh
Key information

Capacity not yet researched — use Refresh equipment & project status (AI).

AEMO status Publicly Announced
Project status Development (AI)

DUID
Owner ARK Energy Corporation Pty Ltd
Commissioned
Expected closure
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM
Turbine model
Stats window
03 Jun 2026 22:35 → 04 Jun 2026 22:35 AEST

Dispatch & revenue

03 Jun 2026 22:35 → 04 Jun 2026 22:35 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.53/MWh
Capex total (greenfield)
$600.64M

Shown in table
$600.64M (2026 real AUD)

Reported / source value
$569.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Owner/developer announced project capital cost of $569 million.

Reference
Bowmans Creek Wind Farm approved | Ark Energy (high confidence)
Source recorded 04 Jun 2026

Capex refurbishment
Capex / MW
$1,732,760

Shown in table
$1.73M (2026 real AUD)

Reported / source value
$1.64M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated from reported total project cost and user-supplied capacity.

Reference
Bowmans Creek Wind Farm approved | Ark Energy (high confidence)
Source recorded 04 Jun 2026

Fixed OPEX (annual)
$20.11M

Shown in table
$20.11M (2026 real AUD)

Reported / source value
$19.07M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$58,017

Shown in table
$58.0k (2026 real AUD)

Reported / source value
$55.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Server-side fallback default supplied by user instructions; no project-specific O&M source located in search results.

Variable OPEX / MWh
$0.53

Shown in table
$0.53 (2026 real AUD)

Reported / source value
$0.50 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Server-side fallback default supplied by user instructions; no project-specific O&M source located in search results.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 04 Jun 2026

Notes
Stage 1 of Bowmans Creek Wind Farm was approved in February 2024 and described by Ark Energy as a $569 million project for 54 turbines and 347 MW. The per-MW capex is calculated from the reported total cost and the site capacity provided (346.64 MW). No project-specific O&M benchmark was found in the searched sources, so fallback default O&M was used for fixed and variable values.

Sources