Blind Creek Solar Farm and Battery Energy Storage System

BESS · Ms BCSF Holdings Pty Ltd as trustee for the Blind Creek Solar Farm Trust · Storage - Battery

Development AEMO: Publicly Announced Solar - Solar NEM data · 30 days
378/486 MW
Researched capacity / storage
Est. SRMC
$0.21/MWh
Key information
Capacity (AI)
378 MW / 486 MWh

User-provided AEMO spreadsheet values for Blind Creek Solar Farm and Battery Energy Storage System (378 MW / 486 MWh).

AEMO status Publicly Announced
Project status Development (AI)

AEMO registration label is Publicly Announced; no primary-source evidence found of construction or commissioning.

Coordinates —

DUID —
Owner Ms BCSF Holdings Pty Ltd as trustee for the Blind Creek Solar Farm Trust
Commissioned —
Expected closure —
Closure date —
Technology Storage - Battery
Fuel Solar - Solar
Module OEM —
Module / inverter supplier —
Inverter OEM —
Inverter model —
Equipment confidence low
Stats window
26 Aug 2026 20:15 → 25 Sep 2026 20:15 AEST

Dispatch & revenue

26 Aug 2026 20:15 → 25 Sep 2026 20:15 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
378 MW / 486 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.21/MWh
Capex total (greenfield)
$438.61M

Shown in table
$438.61M (2026 real AUD)

Reported / source value
$415.80M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Plant-specific build cost not found; left null for total to avoid mixing configuration-specific assumptions.

Capex refurbishment
—
Capex / MWh storage derived
$902,485

Shown in table
$902.5k (2026 real AUD)

Fixed OPEX (annual)
$7.18M

Shown in table
$7.18M (2026 real AUD)

Reported / source value
$6.80M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$18,987

Shown in table
$19.0k (2026 real AUD)

Reported / source value
$18.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used internal default because fixed O&M benchmark extraction for battery storage (for the relevant duration) was not fully resolved into the required per-MW-year figure for this asset.

Variable OPEX / MWh
$0.21

Shown in table
$0.21 (2026 real AUD)

Reported / source value
$0.20 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used internal default variable O&M because battery variable O&M per MWh not extracted from AEMO ETC/O&M review in current search results.

Fuel cost / GJ
—
Heat rate GJ/MWh
—

Confidence: low · Status: ai estimated · Capex basis: default · AI checked 04 Jun 2026

Notes
Project is development-stage (no clear commissioning date found in sources searched). AEMO/CSIRO ETC review provides battery CAPEX/OPEX benchmarks for co-located BESS; however mapping to this exact plant’s solar+storage configuration and splitting per-MW storage basis requires additional confirmation. Used provided internal defaults where AEMO benchmark values could not be reliably extracted for this technology+duration basis for the requested fields.

Sources