Baking Board Solar Farm Chinchilla (BAKING1)

Solar · Chinchilla Solar Pty Ltd · Solar PV - Single axis tracking

Operational AEMO: In Service QLD1 Solar - Solar NEM data · 24 hours
15 MW
Registered nameplate capacity
Est. SRMC
$0.00/MWh
Key information
Capacity
15 MW

AEMO status In Service
Project status Operational (AI)

Region QLD1
Coordinates

DUID BAKING1
Owner Chinchilla Solar Pty Ltd
Commissioned Sep 2018
Expected closure 2044
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM
Module / inverter supplier
Inverter OEM
Inverter model
Stats window
21 Jun 2026 10:20 → 22 Jun 2026 10:20 AEST

Dispatch & revenue

21 Jun 2026 10:20 → 22 Jun 2026 10:20 AEST

No dispatch data for DUID BAKING1 in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
15 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$32.40M

Shown in table
$32.40M (2026 real AUD)

How this was derived
Reported nominal project value/capex for Chinchilla Solar Farm at commercial operations, including development scope.

Reference
IIG Solar Asset Fund - Information Memorandum (2nd Round) (high confidence)
Source recorded 04 Jun 2026

Capex refurbishment
Capex / MW derived
$2,204,082

Shown in table
$2.20M (2026 real AUD)

How this was derived
Per-MW figure is a calculation using reported capex and the user's supplied AC capacity; source reports project value and DC capacity.

Reference
IIG Solar Asset Fund - Information Memorandum (2nd Round) (medium confidence)
Source recorded 04 Jun 2026

Fixed OPEX (annual)
$238.8k

Shown in table
$238.8k (2026 real AUD)

How this was derived
Because the CSF fixed annual O&M fee is not public, a current AEMO/Aurecon mid-size solar default is used as an estimate.

Reference
2024 Energy Technology Cost and Technical Parameter Review - Solar (medium confidence)
Source recorded 04 Jun 2026

Fixed OPEX / MW-yr
$16,245

Shown in table
$16.2k (2026 real AUD)

How this was derived
Per-MW AC estimate is derived from the AEMO/Aurecon DC-based default and the user's 14.7 MW capacity.

Reference
2024 Energy Technology Cost and Technical Parameter Review - Solar (medium confidence)
Source recorded 04 Jun 2026

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

How this was derived
Variable O&M is modelled as zero separately because AEMO/Aurecon includes it within fixed O&M for the solar default.

Reference
2024 Energy Technology Cost and Technical Parameter Review - Solar (medium confidence)
Source recorded 04 Jun 2026

Fuel cost / GJ
$0.00

Shown in table
$0.00 (2026 real AUD)

How this was derived
No fuel supply arrangement is applicable for the solar PV project; revenue arrangements are electricity and LGC market sales.

Reference
IIG Solar Asset Fund - Information Memorandum (2nd Round) (high confidence)
Source recorded 04 Jun 2026

Heat rate GJ/MWh

How this was derived
Solar PV converts solar energy to electricity without a combustible fuel heat input, so heat rate is not meaningful.

Reference
Emissions and energy types (medium confidence)
Source recorded 04 Jun 2026

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 04 Jun 2026

Notes
Generator-specific capex is available from the IIG Solar Asset Fund Information Memorandum for Chinchilla Solar Farm (CSF): A$32.4 million all-in development cost expected at commencement of commercial operations, for a 19.9 MWdc single-axis tracking project. Capex per MW is calculated against the user's supplied registered capacity of 14.7 MW AC: 32.4m / 14.7 = A$2.204m/MW AC; on a DC basis it is about A$1.628m/MWdc. Exact generator-specific O&M dollar fee was not disclosed; the IM says Gildemeister O&M was for a fixed annual fee escalating with CPI and with a 98% performance guarantee. Therefore fixed O&M is estimated using AEMO/Aurecon 2025 mid-size 20 MW ground-mount solar default of A$12,000/MWp DC/year, applied to reported 19.9 MWdc = A$238,800/year; per MW-year shown in profile is this annual estimate divided by 14.7 MW AC. Variable O&M is set to 0 because the AEMO/Aurecon solar default includes variable O&M in the fixed component. Heat rate and thermal efficiency are not applicable to solar PV. Emissions intensity is direct operational Scope 1 only and set to zero for a non-combustion solar PV generator. Closure/refurbishment: project documents assumed 30-year asset life, 30-year lease series, and export services to September 2047; AEMO/Aurecon notes utility solar may be extended toward 40 years subject to condition assessment, with possible inverter, tracker/pile, substation and SCADA refurbishments. Public sources conflict or are incomplete on current status: GEM lists the plant as operating, AEMO 2026-27 MLF still lists BAKING1, while Nemstats search results showed an expected closure date in 2025 and its opened page showed capacity 0/no recent dispatch; this needs direct verification from the latest AEMO generation/closure spreadsheets or market data.

Sources