Gas Peakers · Ti Tree Bioenergy · Reciprocating Engine - Compression ignition
13 Jun 2026 15:20 → 14 Jun 2026 15:20 AEST
| Capex total (greenfield) |
$5.70M
Shown in table Reported / source value How this was derived |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$4,746,835
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$88.6k
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$73,840
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$5.27
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
$8.44
Shown in table Reported / source value How this was derived |
| Heat rate GJ/MWh |
14.00
Shown in table How this was derived |
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 06 Jun 2026
Notes
Plant-specific greenfield capex could not be verified from owner, developer, or government sources in the available search results. Ti Tree Bioenergy states the site has operated since 2002, and an Edina announcement in 2017 confirms a 1.2 MW engine addition to existing 3 x 1.15 MW engines; however, no total project investment figure was found for the original plant or the 2017 expansion. Operating cost and performance assumptions therefore use the provided fallback defaults. The facility was established in Willowbank in 2002.