Other Generators · Mackay Sugar Ltd · Turbine - Steam Sub Critical
08 Jun 2026 04:30 → 15 Jun 2026 04:30 AEST
| Capex total (greenfield) |
$185.19M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$4,115,226
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$14.33M
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX / MW-yr |
$318,488
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$21.28
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Mackay Sugar/Queensland Government source states contracts were issued in February 2010 for a $120 million power plant at Racecourse Mill to generate more than 90 MW of electricity from sugar cane waste; plant details in the same release indicate a new steam turbine generator and 65 MW thermal / 27 MW electric output. No separate plant-specific refurbishment cost identified. O&M values were not found specifically for Racecourse Mill, so AEMO 2024 biomass/biorefinery-type benchmark values were used as a fallback for a steam-biomass cogeneration plant; fixed O&M was interpreted from the AEMO review's annual fixed O&M figure for the relevant biomass/steam generation case and converted to a per-MW basis using 45 MW capacity.