Limondale BESS (LIMBESS1)

BESS · LIMONDALE BATTERY PTY. LTD · Storage - Battery

Commissioning AEMO: Committed NSW1 Other - Other NEM data · 3h
50/400 MW
Registered nameplate capacity / storage
3h revenue
$906
Capacity factor
13.3%
Revenue / MWh
$45.33
Est. SRMC
$1.50/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
50 MW / 400 MWh

AEMO status Committed
Project status Commissioning (AI)

RWE press release, 2026-05-27: received sign-off from AEMO and Transgrid to operate at full capacity after commissioning.

Region NSW1
Coordinates

RWE project page: located near Balranald, New South Wales (no precise coordinates provided in supplied sources).

MLF 0.8568
DUID LIMBESS1
Owner LIMONDALE BATTERY PTY. LTD
Commissioned Dec 2025
Expected closure 2046
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM Tesla
Battery platform / chemistry Megapack
Inverter OEM
Inverter / PCS model
Equipment confidence high
Stats window
03 Aug 2026 00:00 → 03 Aug 2026 03:25 AEST

Dispatch & revenue

03 Aug 2026 00:00 → 03 Aug 2026 03:25 AEST

Energy revenue (× MLF)
$906
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
20.0 MWh
Available
MWh
Curtailed
0.3 MWh
Curtailment
of available
MLF used
0.8568
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • State of chargeINITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2025-09-23 0.9280
2026-07-01 0.8568

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
50 MW / 400 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield) default
$140.00M

Shown in table
$140.00M (2026 real AUD)

Capex refurbishment
Capex / MWh storage default
$350,000

Shown in table
$350.0k (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$25,000

Shown in table
$25.0k (2026 real AUD)

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: unknown · Status: needs review · Capex basis: unknown