Kogan Creek (KPP_1)

Coal · Kogan Creek Power Station Pty Ltd · Turbine - Steam Super Critical

Operational AEMO: In Service QLD1 Fossil - Black Coal NEM data · 24 hours
744 MW
Registered nameplate capacity
24 hours revenue
$716.6k
Capacity factor
53.8%
Revenue / MWh
$74.58
Est. SRMC
$52.60/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
744 MW
AEMO status In Service
Project status Operational (AI)

Region QLD1
MLF 0.9737
DUID KPP_1
Owner Kogan Creek Power Station Pty Ltd
Commissioned
Expected closure 2025-07-02
Closure date
Technology Turbine - Steam Super Critical
Fuel Fossil - Black Coal
Steam turbine OEM
Turbine / boiler supplier
Stats window
03 Jun 2026 18:25 → 04 Jun 2026 18:25 AEST

Dispatch & revenue

03 Jun 2026 18:25 → 04 Jun 2026 18:25 AEST

Revenue (× MLF)
$716.6k
Dispatched
9,607.9 MWh
Available
7,563.0 MWh
Curtailed
244.3 MWh
Curtailment
3.2%
of available
MLF used
0.9737
end of period

Revenue (× MLF)

Estimated $ per interval using regional RRP and MLF effective on each day.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF. Chart uses MLF effective on each interval’s date; summary total uses MLF as at the end of the selected period (same as the revenue list).
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9692
2025-07-01 0.9737

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Black coal
Capacity
744 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$52.60/MWh
Capex total (greenfield) default
$2,604.00M

Shown in table
$2,604.00M (2026 real AUD)

Capex refurbishment
Capex / MW default
$3,500,000

Shown in table
$3.50M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$4.00

Shown in table
$4.00 (2026 real AUD)

Fuel cost / GJ default
$4.50

Shown in table
$4.50 (2026 real AUD)

Heat rate GJ/MWh default
10.80

Shown in table
$10.80 (2026 real AUD)

Confidence: unknown · Status: needs review · Capex basis: unknown