BESS · UPPER BURDEKIN WIND FARM PTY LTD · Storage - Battery
07 Jun 2026 18:45 → 14 Jun 2026 18:45 AEST
| Capex total (greenfield) |
$1,310.04M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage |
—
|
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr |
$27,293
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$1.64
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Project-specific capital expenditure was identified for the Gawara Baya / Upper Burdekin project as $1.2 billion nominal AUD. The available official source describes Gawara Baya as a wind project and does not clearly separate the BESS component or provide the battery-specific MWh capacity, so this capex should be treated as covering the broader project rather than a battery-only unit. No verified battery-specific O&M, storage MWh, heat rate, fuel cost, or asset life source was found in the searched results; server-side defaults were used only for O&M fallback values.