Other Generators · South Australian Water Corporation · Reciprocating Engine - Spark ignition
14 Jun 2026 00:00 → 14 Jun 2026 23:59 AEST
| Capex total (greenfield) |
$5.85M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
$5.85M
Shown in table Reported / source value How this was derived Reference |
| Capex / MW derived |
$779,436
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$1.39M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$185,654
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$14.55
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ default |
$6.00
Shown in table |
| Heat rate GJ/MWh |
9.37
Shown in table How this was derived Reference |
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Plant-specific greenfield capex was not found for the full 7.5 MW unit. The only explicit project cost located was SA Water's $4.7 million Bolivar anaerobic digester upgrade (a brownfield refurbishment, not original plant construction), so that figure is captured as refurbishment capex rather than greenfield capex. Operating assumptions are based on AEMO/Aurecon 2024 bioenergy/waste-to-energy benchmarks, with Bolivar-specific evidence that the site uses biogas and on-site gas engines to generate electricity.