Bolivar Waste Water Treatment

Other Generators · South Australian Water Corporation · Reciprocating Engine - Spark ignition

Operational AEMO: In Service Renewable Biomass or Waste - Biogas NEM data · 24 hours
8 MW
Registered nameplate capacity
Est. SRMC
$70.78/MWh
Key information
Capacity
8 MW

AEMO status In Service
Project status Operational (AI)

Coordinates

DUID
Owner South Australian Water Corporation
Commissioned
Expected closure 2045
Closure date
Technology Reciprocating Engine - Spark ignition
Fuel Renewable Biomass or Waste - Biogas
Plant supplier
Boiler / turbine equipment
Stats window
14 Jun 2026 00:00 → 14 Jun 2026 23:59 AEST

Dispatch & revenue

14 Jun 2026 00:00 → 14 Jun 2026 23:59 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Waste / landfill gas
Capacity
8 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$70.78/MWh
Capex total (greenfield)
$5.85M

Shown in table
$5.85M (2026 real AUD)

Reported / source value
$4.70M (2021 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
$5.85M

Shown in table
$5.85M (2026 real AUD)

Reported / source value
$4.70M (2021 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
SA Water explicitly reported a $4.7 million Bolivar anaerobic digester upgrade, which is a brownfield refurbishment rather than initial greenfield construction.

Reference
Hundred tonne tank topper lifted to SA Water record (high confidence)
Source recorded 06 Jun 2026

Capex / MW derived
$779,436

Shown in table
$779.4k (2026 real AUD)

Reported / source value
$626.7k (2021 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$1.39M

Shown in table
$1.39M (2026 real AUD)

Reported / source value
$1.32M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$185,654

Shown in table
$185.7k (2026 real AUD)

Reported / source value
$176.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO/Aurecon bioenergy section provides annual fixed O&M for biogas digester / bioenergy pathways; used as benchmark operating assumption.

Reference
2024 Energy Technology Cost and Technical Parameter Review (high confidence)
Source recorded 06 Jun 2026

Variable OPEX / MWh
$14.55

Shown in table
$14.55 (2026 real AUD)

Reported / source value
$13.79 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Benchmark variable O&M for waste-to-energy/bioenergy pathway used for the plant.

Reference
2024 Energy Technology Cost and Technical Parameter Review (high confidence)
Source recorded 06 Jun 2026

Fuel cost / GJ default
$6.00

Shown in table
$6.00 (2026 real AUD)

Heat rate GJ/MWh
9.37

Shown in table
$9.37 (2026 real AUD)

How this was derived
Used as a proxy for spark-ignition biogas reciprocating-engine thermal input rate.

Reference
2024 Energy Technology Cost and Technical Parameter Review (medium confidence)
Source recorded 06 Jun 2026

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Plant-specific greenfield capex was not found for the full 7.5 MW unit. The only explicit project cost located was SA Water's $4.7 million Bolivar anaerobic digester upgrade (a brownfield refurbishment, not original plant construction), so that figure is captured as refurbishment capex rather than greenfield capex. Operating assumptions are based on AEMO/Aurecon 2024 bioenergy/waste-to-energy benchmarks, with Bolivar-specific evidence that the site uses biogas and on-site gas engines to generate electricity.