Banimboola (BAPS)

Other Generators · AGL Hydro Partnership · Hydro - Dam

In Service VIC1 Hydro - Water NEM data · 24 hours
2 MW
Registered nameplate capacity
Est. SRMC
$0.00/MWh
Key information
Capacity
2 MW
Status In Service
Lifecycle Operating
Region VIC1
DUID BAPS
Owner AGL Hydro Partnership
Commissioned
Expected closure 2025-07-02
Closure date
Technology Hydro - Dam
Fuel Hydro - Water
Turbine OEM
Turbine type / model
Stats window
03 Jun 2026 16:25 → 04 Jun 2026 16:25 AEST

Dispatch & revenue

03 Jun 2026 16:25 → 04 Jun 2026 16:25 AEST

No dispatch data for DUID BAPS in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Hydro
Capacity
2 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$23.00M

How this was derived
Primary news report provides the reported nominal project cost and construction/commissioning context in 2005.

Reference
$23m power station nearly up and running (high confidence)

Capex refurbishment
Capex / MW
$1,885,246

How this was derived
Derived unit capex: 23,000,000 / 12.2 = 1.885 million AUD/MW, nominal 2005.

Reference
$23m power station nearly up and running (medium confidence)

Capex / MWh storage
Fixed OPEX (annual)
$575.0k

How this was derived
No Banimboola-specific O&M found. A midpoint/default 2.5% of AUD 23.0m capex gives AUD 575,000/year for the station.

Reference
Renewable Power Generation Costs in 2024 (low confidence)

Fixed OPEX / MW-yr
$47,131

How this was derived
Default estimate only: AUD 575,000/year divided by 12.2 MW = AUD 47,131/MW-year.

Reference
Renewable Power Generation Costs in 2024 (low confidence)

Variable OPEX / MWh
$0.00

How this was derived
No Australian Banimboola-specific VOM was found; zero/marginal VOM is a generic hydro modelling assumption.

Reference
Cost and Performance Characteristics of New Generating Technologies, Annual Energy Outlook 2020 (low confidence)

Fuel cost / GJ
$0.00

How this was derived
Owner explanation supports treating water as non-purchased fuel for fuel-cost purposes.

Reference
Hydroelectric Power Stations (high confidence)

Heat rate GJ/MWh

How this was derived
Heat rate is a thermal-plant metric and is not applicable for Banimboola hydro.

Reference
Hydroelectric Power Stations (high confidence)

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 04 Jun 2026

Notes
Reported capex is for the whole Banimboola Power Station, not just the 2.2 MW unit. AGL and ESC sources identify Banimboola as a 12.2 MW hydro power station comprising two 5 MW units and one 2.2 MW unit; therefore capex per MW is calculated as AUD 23.0m / 12.2 MW. The user-supplied 2.2 MW appears to be the small unit capacity rather than total station/DUID capacity. Fixed O&M is not generator-specific; estimated as 2.5% of reported capex per year, a midpoint/default within published hydropower O&M percentage ranges, and should be reviewed. Variable O&M and fuel cost are assumed zero/marginal for dispatch modelling because hydropower O&M is typically treated as fixed and there is no combusted fuel. Heat rate and thermal efficiency are not applicable to hydro. Emissions intensity is direct operational Scope 1 combustion emissions, assumed 0 tCO2e/MWh; lifecycle emissions can be non-zero and site-specific, particularly for reservoirs. No Banimboola-specific major refurbishment or closure notice was found; AGL describes the station as operating since 2005. AGL page lists average annual output as 11 GWh, while older secondary references report 35 GWh; AGL owner data is preferred.

Sources